I have been working all hours over the past few weeks to try to clear my backlog of orders and projects. Here are the results and there is still a little way to go. Please understand I work alone and everything is done by me except for photo-etching, bronze investment casting, flag and 88 mm round production.
Feifil Unit Metal Casting. This is as far as I got yesterday when I ran out of raw metal. New metal will be ordered on Monday.
Large Cast Parts.

Small Cast Parts completed.

Tiger 1-2 Cupola Castings. This completes current orders. 16 cupolas already delivered.
Tiger 1 Stowage Bins. 7 current orders delivered, 5 kits available. 61 Bins sold to date.

Panzer III Parts and Tiger 2 Grills ready for production.

Panther Tools and Accessory Sets under production.

Tiger 1 Grill Sets under production.

Metal Cast Parts Bins.
Tiger.



Panther and General.

Panzer IV.

SD250 and Misc.

Small photo-etched parts all types

Packaged parts Bins.
Tiger.


SD250.

General.

Panzer IV.

Tiger and Panther Cupola Parts. Plus Tow Ropes.

Current orders under production. I have only shown those with finished parts. There are about 20 other I have not started on yet.


The only project I am having problems with is the Panther Cupola which is my doing. I tried to make it to accurate and what I am trying to do is very time consuming to achieve. I will get there I hope by the end of the month.